In Nigeria, the 9 inches hollow block (450mm x 225mm x 225mm) is normally used for the construction of blockwork of buildings exceeding one storey. The length of the block is 450mm (18 inches), the height is 225mm (9 inches), and the width is 225mm (9 inches). Contractors and builders are often faced with the challenge of either buying blocks for construction or moulding it on their own. When the conditions are right, builders will prefer to mould their own blocks, especially for the purpose of controlling the quality of the blocks, and to reduce the cost of transportation.
Let us assume that you have decided to mould your own blocks, and you have been faced with the challenge of estimating the quantity of cement and sand to purchase that will satisfy the construction requirement. This article will give you a guide on how to estimate the quantity of sand and cement required for moulding blocks in Nigeria. I am going to work through the steps, so that you will be able to make calculations just in case you are using any other size of block.
Initial data
Number of blocks required = 3000 pieces
Recommended production = 1 bag of cement to produce 35 blocks
Step 1: Calculate the volume of the block
For the block size shown above;
Volume of block without holes = (0.45 × 0.225 × 0.225) = 0.02278125 m3
Volume of holes = 2(0.225 × 0.125 × 0.15) = 0.0084375 m3
Therefore volume of the block = 0.02278 – 0.0084375 = 0.0143 m3
Step 2: Calculate the volume of the 35 blocks
If the volume of 1 block is 0.0143, the volume of 35 blocks = (0.0143 × 35) = 0.502 m3
Step 3: Calculate the volume sand required for the 35 blocks
The volume of 1 bag of cement is 34.72 litres = 0.03472m3.
This is obtained by knowing that the mass of 1 bag of cement = 50kg, and the density = 1440 kg/m3
The volume of a standard builder’s wheelbarrow is 0.065 m3 (unheaped). We assume that approximately 2 bags of cement (4 head pans of cement) will fill one builder’s wheelbarrow. Now, we can estimate the number of wheelbarrow trips of sand that the moulder should provide in order to make 35 blocks from one bag of cement.
Total volume of 35 blocks required = 0.502 m3
Let the number of wheel barrow trips of sand be x
Hence, (volume of 1 bag of cement) + (Total volume of sand) = Volume of 35 blocks
Hence, 0.03472 + x(0.065) = 0.502 m3
On solving, x = 7.1889 unheaped wheelbarrow trips of sand
The volume of sand required to make 35 blocks = 7.1889 × 0.065 = 0.46728 m3
However, note that this leads to a mix ratio of about 1:14 which will not be very good when subjected to a compressive strength test. The ideal mix ratio for blocks for proper strength should be about 1:10 or 1 bag to 25 blocks.
Step 4: Calculate the total volume of materials required
We can therefore estimate the quantity of materials to be purchased;
If 1 bag of cement is needed for 35 blocks, therefore 86 bags of cement is needed to mould 3000 blocks (gotten by 3000/35)
If 0.46728 m3 of sand is required to make 35 blocks, therefore, 41 m3 of sand (about 67.60 tonnes assuming the density of dry sand = 1600 kg/m3) is needed to make 3000 blocks.
For a 5 tonne tipper of 3.8 m3 capacity, we have to order for 11 trips of sharp sand.
You have to be very sure of the size of the tipper that will be delivering the sand to you in order to make your estimates more reasonable. On the other hand, you can make the considerations for variations between the weight of materials when wet and when dry. However, this will never be critical for block moulding based on experience. But in concrete it can be very considerable.
Therefore summarily, we need 86 bags of cement and 68 tonnes of sand to mould about 3000 pieces of 9 inches blocks with holes (for 1 bag = 35 blocks).
Thank you for reading, and God bless.
READ ALSO IN THIS BLOG
How to calculate the number of blocks required for the construction of a 3 bedroom flat
Visit our Facebook fan page on
www.facebook.com/structville
kindly help with the section for 150 mm block .. Nice analysis I commend your simplicity
I expected to thank you for this extraordinary read. I positively getting a charge out of every single bit of it I have you bookmarked to take a gander at new stuff you post. Iron Castings
Very nice and simile accurate analysis. Thank you very much.
It's cool
Please whats the total cost for 3 bed, 2bed and 1 bed building?
Contact me for that it is extremely professional knnamdi1@gmail.com
sir how do you get 41m3 of sand and 7.1889 unheaped wheelbarrow
so dont we need granite if you are trying to fence a 4 and half plot, because we need cement , sharp sand , water dont we need granite
• Hi! I'm at work browsing your blog from my new apple iphone!
Just wanted to say I love reading through your blog and look forward to all your posts!
Keep up the superb work!
Point Cloud to BIM conversion in USA
ANIMATION SERVICES in USA
BIM Implementation in USA
The smalles Tipper is 3.8m3 by volumn weighing, it means to know the no of tips that make up 41m3, devide it by 3.8 = 11 Tips
Well explained. Looking forward to see topics like 'structural arch design'
Very well done. Absolutely brilliant information. I'm in love with this blog. they always provide such a great information.
Chettinad group
Chettinad group
What is your sand-cement mix ratio?
Awesome
I really do appreciate your work. Please sir, how many head pan of sand will make 30 9 inches block and 40 6 inches block. Thank looking forward to hearing from you.
Thanks for the useful technical information, but is it technical, or as an advice to add more trips, simply because most bucket been used to deliver sand some as deformed and reduced in size. So that someone we not lost at the end of moulding. THANKS
steps to taking to achieve the block moulding of 6 and 9 inches block
This is so so clearly written and easy to understand.Very Very Helpful for a Qs like me.God increase you.
Good estimation Sir. But our Target was in one bag, 35 blocks should be obtained. But after calculations, 14 wheelbarrows per bags were obtained and you reduce it to 10 wheelbarrows, with that will you still arrive at the same total volume required for the molding, and expected number blocks (35 per block)?
I mean 35 per bag.
How many wheelbarrow of sand will mould 35 pieces of 9 inches block ?
I’m not an Engr but I need straightforward answer so I can instruct my worker on what to do.
14 wheelbarrow of sand
I am really impressed with the simplicity and professionalism of your write-ups. Brilliant!!
well done Engr. i really appreciate your work. more grace Sir
What about 6inch block par bag of cement?
Many thanks
Well detailed. Nice one.
This is below par, considering details on ur bio. You didn’t take note of mix ratio or recommended compressive strength. Cos from this write up, it is a evident that adopted mix ratio is 1:13.5 or higher whereas NIS 87: 2000 recommends 1:8 maximum mix ratio. You also failed to educate them on the best curing practice to achieve a good compressive strength.
First of all, you didn’t read the article properly before writing your comment. Secondly, you didn’t understand the purpose of the article. Thirdly, I have doubts if you are actually involved in practical building construction in Nigeria. The standards you stated are in order for best practice anyway, kudos.
How many tonnes of sand do I need to set 2500 quantity of blocks pls if I may ask ?
Wow, thank you from Kenya for this informative article Sir. I wanted to mould blocks but with cement, quarry dust and sand at a recommended ratio of 1:2:3 which I’m told will give me an average of 25 solid blocks.
Kindly advise me on this please ??.
Thank you and God bless.
I must say kudos to the writer if this….you’re a good teacher..its so intresting and explanatory
I need your insightful blog on cost estimate of building
How many wheelbarrows of sand make up a 6 tyres truck/tipper
Highly educative Sir! Thanks for your efforts in the landscape of engineering.
I love it
Sir please how many trip of sand and how many bags of cement will I used to get 4000 blocks