Sequence and Method of Erection of Steel Structures

The sequence and methods of erection of steel structures are generally dependent on the layout and arrangement of the structural components. Erection of steel structures involves the on-site installation of steel members into a frame. Lifting and positioning the individual components into position, then joining them together, are all part of the process. Bolting is the most common method, however, site welding is also employed.

Generically, the erection of steel structures consists primarily of four tasks:

  1. Ensure that the foundations are suitable and safe before starting the erection process.
  2. Generally, cranes are used to lift and place components into place, however, jacking is also used. Bolted connections can be used to secure components in place, but they will not be fully tightened. Similarly, bracings may not be completely secure.
  3. Aligning the building, primarily by making sure that the column bases are lined and level, and that the steel columns/stanchions are plumb. To allow for column plumb adjustment, the packing in beam-to-column connections may need to be modified.
  4. Bolting-up the frame by ensuring that all bolted connections are fully installed in order to secure and make the frame rigid.
Steel structure construction

Normally, the following sequence and method of erection are followed;

Sequence for Erection of Steel Structures

Stage 1:
Before the steelwork erection commences, the sizes and exact locations of the holding-down bolts on the foundation and base plates are double-checked. Sometimes, discrepancies can occur due to errors from setting out thereby causing the erection timetable to be delayed. Following these checks, the following procedures are carried out:

  • Install the columns on the base plates.
  • Align the columns properly to be straight and plumb.
  • Under the base plate, adjust the holding-down bolts with adjustable screws to maintain the required grout gap between the bottom of the base plate and the foundation.
  • Use temporary bracings to keep the columns true to their vertical position and prevent them from swaying in any direction.
  • The columns or stanchions are erected in parts and fastened together on site when they are quite long.

Stage 2:
Install the central portion of each rafter. When trusses are to be used, the whole section may be erected in one piece after fabrication on the ground.
Connect the truss to the column ends with bolts to form the full structural frame.

Stage 3:
After final alignments and adjustments of the frame placements, install the vertical column bracing and roof bracings to make the entire structure stable.

Stage 4:
Use bolted connections to secure all roof purlins and sheeting rails to the framework.

Stage 5:
If necessary, erect gantry crane girders (for industrial buildings and warehouses).

Stage 6:
Install the overhead cranes on the crane girders where required.

Stage 7:
Install the roof and side panels.

Stage 8:
After the erection is complete, fill the undersides of the base plates with non-shrink grout.

Normal construction follows the erection sequence outlined above. After preparing an erection program, a special sequence should be followed in the case of special constructions.

Lifting of Steel Members

Cranes and Mobile Elevating Work Platforms (MEWPs) are commonly used for the erection of steel structures, even though other methods may be utilized for steel bridge construction. Cranes are generally categorized into two categories: mobile and non-mobile. Truck-mounted cranes, crawler cranes, and all-terrain cranes fall into the first group, whereas tower cranes fall into the second.

Crane lifting a heavy steel member

The number of crane lifts required determines typical erection speeds and, as a result, the site programme of works. Pre-assembled units should be used to the maximum extent possible to reduce the number of crane lifts. If crane availability is an issue, steel decking, which can be installed by hand, is a better option than precast concrete units, which require a crane for individual placement. The designer can utilize a ‘piece count’ to estimate the number of lifts required and thus the erection time.

Alignment and Plumbing

Lining, leveling, and plumbing involve collaboration between the site engineer, who uses a survey instrument, and the erection crew, who tightens and shimmies the last bolts. The erection gang persuades the frame to move to a position acceptable to the checking engineer by using wedges, jacks, pull-lifts, and proprietary pulling devices such as Tirfors, and then bolts it up firmly. Some misalignment is overcome, and some are produced, as a result of this process. If the latter is unfavorable, local adjustments are made.

Connections

Bolted Connections
Bolted connections are preferable to site welding because it is faster, less sensitive to bad weather, and have less access restrictions and inspection requirements.

Property class 4.6 and 8.8 non-preloaded bolts to BS EN 15048 are commonly used in 2 mm clearance holes in structural bolting operations (for buildings) in the UK. M20 8.8 completely threaded bolts, which are the recommended solution, are widely accessible. Bolts with property class 4.6 are typically used only for fixing lighter components like purlins or sheeting rails, when 12 mm or 16 mm bolts can be used instead.

Bolting during erection of steel structures
Bolting of steel beams on site

Fully threaded bolts are commonly specified, implying that one bolt size can be used for a wide range of connections. It is advised that M20, 8.8 completely threaded bolts 60 mm long be used, as they can be used to make roughly 90% of basic connections. Preloaded bolts should only be utilized in situations where relative movement of linked parts (slip) is objectionable or if dynamic loading is a possibility.

It is best to avoid using different grade bolts of the same diameter on the same project. With non-preloaded bolts in typical clearance holes, washers are not required for strength. Bolts, nuts, and washers should be supplied with a corrosion-resistant coating that does not require further protection on-site when possible.

Welded Connections
If bolted connections can be made, site welding is usually avoided. When site welding is used, it is necessary to provide cover from bad weather as well as good access for both welding and inspection. Apart from the extra cost implications, providing such protection and access may have program consequences.

Erection Handover

The final goal of the erection process is to hand over the frame in good working order to the subsequent trades. The crucial criterion here is the erected frame’s positional precision, which is dependent on an understanding of how a steel frame’s erected position is regulated.

A steel-framed structure is a massive structure made up of a huge number of relatively thin and flexible components. Plumb and line accuracies of about 1 part in 1000 are targeted for the completed construction, employing components that can be fabricated with greater variability than 1 part in 1000 separately. Deformations such as the flexure of the structure under the self-weight of steel also have an impact on its real position.

Tests performed upon handover of a built steel structure could be deemed final under an inspection and test plan. All tests must have the following information in order to be meaningful:

  • The testing procedure
  • The test’s location and frequency
  • Criteria for Acceptance
  • Actions to be taken if compliance criteria is not obtained

1 COMMENT

  1. very useful and mind opening information, i”m steel structure erection foreman in Gulf. next day i starting my next project

LEAVE A REPLY

Please enter your comment!
Please enter your name here