8.7 C
New York
Thursday, September 19, 2024
Home Blog Page 52

Design of RC Beams for High Shear Load

Reinforced concrete beams in buildings and bridges are predominantly subjected to bending moment and shear forces. When beams are subjected to a very high concentrated load (such as a beam supporting a heavily loaded column), the effects of shear become very critical in the design of such members.

Furthermore, in the absence of transverse reinforcement, shear failure becomes the dominant mode of collapse in heavily reinforced concrete beams. This failure manifests through the formation of diagonal cracks. Due to their brittle nature, shear failures in reinforced concrete beams can lead to catastrophic collapses without adequate warning. The inability to redistribute internal stresses within the member further exacerbates this hazard.

As a consequence, shear failures demand heightened attention from structural engineers, particularly when designing structures where mitigating the risk of abrupt shear collapse is paramount, such as transfer structures or structures subjected to high shear load.

The shear response of reinforced concrete beams exhibits significant complexity and is influenced by a lot of parameters. These factors include, but are not limited to, the ratio of shear span to depth, the percentage of longitudinal reinforcement, the overall member depth, the width of existing cracks, and the presence or absence of transverse reinforcement (stirrups or links).

Due to this inherent complexity, a universally accepted and straightforward theory for predicting shear behaviour is yet to be established. Consequently, a number of international concrete design codes continue to employ empirically derived shear design methodologies.

Shear failure usually occurs in the form of diagonal cracks and must be checked under the ultimate limit state during the structural design of buildings. In reinforced concrete buildings, shear is resisted using links (stirrups). When a design is failing in shear, the following solutions can be adopted;

(1) Increasing the depth of the beam
(2) Increasing the width of the beam
(3) Increasing the area of shear reinforcement provided and/or reducing the spacing of the links.

It is not very common to modify the percentage of longitudinal reinforcement for the purpose of shear resistance.

High Shear Load Resistance According to EC2

Eurocode 2 employs the strut-and-tie model to represent the shear resistance mechanism. In this model, the shear force is resisted by:

  • Concrete compression strut: This imaginary strut, inclined at an angle with respect to the beam axis, transmits compressive forces. The angle varies between 21.8 degrees to 45 degrees.
  • Transverse reinforcement: Stirrups or links provide tensile resistance to prevent the formation and propagation of diagonal cracks.

When the design shear force VEd exceeds the design shear resistance of the concrete section alone (VRd,c), then a shear reinforcement design is required. The design involves providing the spacing and area of stirrups to resist the difference (VEd – VRd,c). Eurocode 2 provides design equations for calculating the required shear reinforcement area (Asw) based on the design shear force, material properties, and inclination of the concrete strut (θ). The code provides limitations on the angle of the concrete strut and the maximum shear force a section can resist.

The maximum allowable strut angle is 45 degrees (cot θ = 1.0). When the strut angle exceeds 45 degrees, a new section will have to be selected. Where necessary, especially under high shear loads, it is important to determine the intermediate (actual) strut angle which depends on the applied shear stress.

Design Example for High Shear Load

BEAM 2BWITH 2BHEAVY 2BSHEAR 2BLOAD

In this article, a beam is loaded at the ultimate limit state as shown above. We are to design support B for shear according to Eurocode 2 and BS 8110. The preliminary design data is given below.

Design Data
:
Concrete Strength = 25 N/mm2
Grade of steel = 500 N/mm2
Width of beam = 300 mm
Depth of beam = 750 mm
Concrete cover = 35 mm

FLEXURAL DESIGN OF SUPPORT B

MEd = 794.5 kN.m

Effective depth (d) = h – Cnom – ϕ/2 – ϕlinks
Assuming ϕ25 mm bars will be employed for the main bars, and ϕ10 mm bars for the stirrups (links)
d = 750 – 35 – (25/2) – 10 = 693 mm

k = MEd/(fckbd2) = (794.5 × 106)/(25 × 300 × 6932) = 0.220
Since k > 0.167, compression reinforcement required

Area of compression reinforcement AS2 = (MEd – MRd) / (0.87fyk (d – d2))

MRd = 0.167fckbd2 = (0.167 × 25 × 300 × 6932) × 10-6 = 602 kNm

d2 = 35 + 12.5 + 10 = 57.5 mm

AS2 = ((794.5 – 602) × 106) / (0.87 × 460 × (693 – 57.5)) = 757 mm2
Provide 4H16 Bottom (Asprov = 804 mm2)

Area of tension reinforcement As1 = MRd / (0.87fyk z) + AS2
Where z = d[0.5+ √(0.25 – 0.882k’)]
k’ = 0.167
z = d[0.5+ √((0.25 – 0.882(0.167))] = 0.82d

As1 = MRd / (0.87fyk z) + AS2 = ( 602 × 106) / (0.87 × 500 × 0.82 × 693) + 757 mm2 = 3192 mm2

Provide 7H25  TOP (ASprov = 3437 mm2)

SHEAR DESIGN ACCORDING EC2

Support B;
VEd = 814 kN

VRd,c = [CRd,c.k.(100ρ1 fck)(1/3) + k1cp]bw.d ≥ (Vmin + k1cp) bw.d

CRd,c = 0.18/γc = 0.18/1.5 = 0.12
k = 1 + √(200/d) = 1 + √(200/693) = 1.53 < 2.0, therefore, k = 1.53
Vmin = 0.035k(3/2) fck0.5
Vmin = 0.035 × (1.53)1.5 × 250.5 = 0.27 N/mm2
ρ1 = As/bd = 3437/(300 × 693) = 0.0165 < 0.02; Therefore take 0.0165

VRd,c = [0.12 × 1.53 (100 × 0.0165 × 25 )(1/3)] × 300 × 693 = 131887 N = 132 kN

Since VRd,c (132 kN) < VEd (814 kN), shear reinforcement is required.
The compression capacity of the compression strut (VRd,max) assuming θ = 21.8° (cot θ = 2.5)

VRd,max = (bw.z.v1.fcd) / (cot⁡θ + tanθ)
V1 = 0.6(1 – fck/250) = 0.6(1 – 25/250) = 0.54
fcd = (αcc fck) / γc = (0.85 × 25) / 1.5 = 14.167 N/mm2
Let z = 0.9d

VRd,max = [(300 × 0.9 × 693 × 0.54 × 14.167) / (2.5 + 0.4)] × 10-3 = 565 kN
Since VRd,c < VRd,max < VEd

We need to modify the strut angle
θ = 0.5sin-1[(VRd,max /bwd)/0.153fck(1 – fck/250)]
θ = 0.5sin-1[(565000/(300 × 693))/3.4425] = 26°

Since θ < 45°, the section is okay for the applied shear stress

Hence Asw / S = VEd / (0.87 fyk z cot θ) = 814000 / (0.87 × 500 × 0.9 × 693 × 2.05 ) = 1.463

Minimum shear reinforcement;
Asw / S = ρw,min × bw × sinα (α = 90° for vertical links)
ρw,min = (0.08 × √(fck)) / fyk = (0.08 × √25) / 500 = 0.0008
Asw/Smin = 0.0008 × 300 × 1 = 0.24
Maximum spacing of shear links = 0.75d = 0.75 × 693 = 520 mm

Provide H10mm @ 100 mm c/c as shear links (Asw/S = 1.57) Ok!!!!

As a means of comparison, let us consider the shear design of the same support according to BS 8110, assuming the same area of tension reinforcement was provided.

SHEAR DESIGN BY BS 8110-1:1997
Design of support B

Ultimate shear force at the centerline of support
V = 814 kN

Using the shear force at the centreline of support;
Shear stress = V/(bd ) = (814 × 103) / (300 × 693) = 3.915 N/mm2

(3.915 N/mm2 ) < 0.8√fcu (4.00 N/mm2 ). Hence, the dimensions of the cross-section are adequate for shear.

Concrete resistance shear stress
vc = 0.632 × (100As/bd)1/3 (400/d)1/4

(100As/bd) = (100 × 3437) / (300 × 693) = 1.653 < 3.0 (See Table 3.8 BS 8110-1;1997)

(400/d)1/4 = (400/693)1/4 = 0.87; But for members with shear reinforcement, this value should not be less than 1. Therefore take the value as 1.0

vc = 0.632 × (1.653)1/3 × 1.0 = 0.747 N/mm2

Let us check;
(vc + 0.4)1.147 N/mm2 < v(3.915 N/mm2) < 0.8√fck (4.00 N/mm2)

Therefore, provide shear reinforcement links.
Let us try 2 legs of T10mm bars (Area of steel provided = 157 mm2)

Asv/Sv = [bv (v – vc)]/(0.87 × fyv) = [300 × (3.915 – 0.747)] / (0.87 × 500) = 2.184

Maximum spacing = 0.75d = 0.75 × 693 = 520 mm

Try 3 legs of T10mm
Provide 3 legs Y10mm @ 100 mm c/c links as shear reinforcement (Asv/Sv = 2.34)

We can therefore see that disregarding load factor and flexural design requirements, EC2 is more economical than BS 8110 in shear design, and in this case study by about 33%.


25 TOP CIVIL ENGINEERING QUESTIONS

Instruction: Attempt All Questions
Examiner: Structville Integrated Services

(1) Mechanics of deformable bodies is usually studied under?
(A) Statics
(B) Strength of Materials
(C) Dynamics

(2) Which structural model is used for assessing shear resistance of RC structures in BS 8110-1:1997?
(A) Strut and Tie Method
(B) Theorem of three moments
(C)  Euler’s Theorem

(3) The vertical deformation of soils per unit pressure is usually referred to as?
(A) Stiffness
(B) Modulus of subgrade reaction
(C) Bearing Capacity

(4) What is the basic unit of flow rate?
(A) m3/s
(B) m2/s
(C) m/s

(5) An S275 hot rolled I-Section has a flange thickness of 20.5mm. What is the design yield strength?
(A) 255 Mpa
(B) 265 Mpa
(C) 275 Mpa

front
Click on the Image to Download Textbook


(6) The natural foundation of a road way is called?

(A) Base
(B) Sub-base
(C) Subgrade

(7) Why are return bars provided at the edges of RC slabs under simply supported assumptions?
(A) To resist torsion
(B) To resist negative moment
(C) None of the above
(D) All of the above

(8) A simply supported beam is pinned at both ends. Therefore the beam is?
(A) Statically determinate
(B) Unstable
(C) Statically indeterminate

(9) How can we control deflection in a solid RC slab?
(A) By increasing the depth of the slab
(B) By introducing compression reinforcements
(C) By increasing the area of tension reinforcement
(D) All of the above


(10) In the design of highway bridges (BS 5400), HA loading comprises of ?
(A) Knife Edge Load and UDL
(B) Tandem Axle Loads
(C) UDL only

(11) In concrete slabs on grade, the most critical loading condition occurs at?
(A) Mid span
(B) Edge
(C) 2.5d from the edge

(12) For a rectangular lamina immersed in a fluid at rest, the hydrostatic thrust passes through?
(A) Centre of pressure
(B) Centroid
(C) Meta Centre

(13) At a construction site, the leveling staff reads +2.45m at point A and +2.76m at point B. Which of the following points is higher in elevation?
(A) Point A
(B) Point B
(C) Depends on the datum

(14) A 0.8m long cantilever beam is subjected a concentrated load of 750 kN at the free edge. Which of the following poses the most serious problem?
(A) Bending
(B) Shear
(C) All of the above

(15) The continuous shear deformation of  a fluid is referred to as?
(A) Pressure
(B) Flow
(C) Turbulence

(16) In the continuous support of a floor beam, how many percent of top tension reinforcement should be allowed into 0.15L of the adjacent spans?
(A) 50%
(B) 65%
(C) 100%

(17) If the diameter of a pile foundation is 400mm, the recommended minimum thickness of the pile cap is?
(A) 900 mm
(B) 750 mm
(C) 400 mm

(18) Punching shear in pad footings is usually checked at?
(A) d from the column face
(B) 1.5 d from the column face
(C) at the column face

(19) The complete loss of shear strength in soils is referred to as?
(A) Earthquake
(B) Settlement
(C) Liquefaction

(20) The deflection of a steel beam depends on?
(A) The elastic Modulus
(B) The length
(C) The support conditions
(D) All of the above

(21) Curtain walls are usually used in high rise building for which of the following reasons?
(A) Aerodynamics of winds
(B) To reduce dead load
(C) Reflection of night sky

(22) In a single span generic beam, deflection is maximum at?
(A) Centre of the beam
(B) Point of maximum moment
(C) Point of zero slope

(23) What is the recommended maximum water/cement ratio for production of concrete for water retaining structures?
(A) 0.4
(B) 0.5
(C) 0.6

(24) The difference between plastic limit and liquid limit in a soil is called?
(A) Activity
(B) Plasticity Index
(C) Cohesion
(D) Shrinkage Limit

(25) Adequate concrete cover to reinforcement does not enhance one of the following in RC structures?
(A) Fire Resistance
(B) Durability
(C) Cracking
(D) None of the above



Strength of Spaghetti Bridge Trusses (Video)

Interestingly, uncooked spaghetti has been used extensively to demonstrate the behavior of structures under the action of externally applied loads.

Investigations have usually included;

(1) Varying the truss configuration to see which one that can resist the greatest load

(2) Varying the span

(3) Increasing the number of spaghetti strands, etc

In this video, a spaghetti bridge was loaded until it fails at a load of 31kg.

Rugged Steel Staircase Construction – What are your thoughts on this?

I stumbled across this steel staircase construction (most probably for an industrial building), and I was intrigued. The massive size of the sections are thought provoking, and the connections look quite interesting.



I will like us to discuss this design and construction by considering the connections, members, details, applicability, and how it could have been improved. Also can you redesign the staircase by assuming a distributed ultimate load of 20 kpa. Assume a floor height of 4m, and verify if the section was overdesigned or not. Thank you as you air your thoughts and design results.

Transfer Structures: Analysis and Design

Transfer structures can be described as structural elements that redirect gravity loads (usually from columns or walls) to other structures (such as beams or plates) for distribution to another supporting structure that can resist the load. In other words, transfer structures alter the load path of gravity loads from one alignment to another.

The prominent issue in the design of transfer structures is that the member transferring the load becomes heavily loaded, thereby demanding a very cautious design. Furthermore, the unconventional load path may unintentionally affect the design and performance of other structural members within the building. This is usually found in high-rise buildings where floor arrangements differ. Structural elements such as beams and slabs are often employed as load transfer structures.

load path
Figure 1: Typical load path in a building

Applications of Transfer Structures

Transfer structures play a crucial role in the design and construction of buildings, especially when faced with complex architectural requirements and structural challenges. These structures are engineered to efficiently transfer loads from one area of a building to another, ensuring structural integrity and stability. From tall skyscrapers to large-scale infrastructure projects, transfer structures have become indispensable elements of modern construction.

The primary purpose of transfer structures is to redistribute the loads imposed on them to different vertical and horizontal components of a building. This redistribution of forces is necessary when there are discontinuities or changes in load paths within a structure. Transfer structures enable the efficient transfer of loads from, for example, columns or walls above to columns or walls below, bypassing obstructions such as openings, large spans, or irregular load distributions.

Design of Transfer Structures

I had my first experience in the design of transfer structures in January 2016, when I was given the project to redesign the Cafeteria Hall of Ritman University Community Centre. The original arrangement of the structure is shown in Figure 2;

image 6
Figure 2: Original Arrangement of the Ground Floor Hall

It was desired to reduce the intermediate columns of the ground floor to a row of single columns as shown in Figure 3. In this case, the beam to support the two rows of internal columns on the first floor can be described as a transfer beam. The two columns so supported can be described as ‘floating columns‘. The transfer beam will be responsible for altering the load path of the internal columns. In some cases, deep beams can be used as transfer structures.

transfer structures
Figure 3: Modified Arrangement of the Ground Floor Hall

On analysis of the transfer beam, I observed a heavy shear force within the intermediate support, which lead to an increase in the depth of the beam, and the provision of heavy longitudinal and shear reinforcement within the region. This modified arrangement is an example of a transfer structure in its simplest term. The floor beam carrying those upper columns could be described as a transfer beam.

Transfer structures should be designed by experienced engineers, especially those who have practical site experience and a very good understanding of the statics of structures. This is mainly because the design of reinforced concrete transfer structures demands that the engineer will manipulate the depth, width, and reinforcements being provided by the design software.

For example, the 5-storey building (G+4) shown below was analysed and designed using Orion Software. The building is a typical transfer structure wherein all the ground floor columns are terminated on the first floor. The rest of the columns started from the first floor and go all the way to the roof. The upper columns are supported on 1.5m long cantilever beams (overhangs) wrapping around the building at the first-floor level (see Figure 4).

typical structural model of a transfer structure
Figure 4: Typical structural model of a transfer structure

For the design of the structure, an initial trial depth of 600 mm was considered for all the first-floor beams and a beam width of 230 mm. The preliminary section failed in flexure and shear as expected for a 5-storey building.

Subsequently, the depth was increased to 750 mm while maintaining the same width of 230 mm. Most of the spans started looking okay (especially for the internal longitudinal/transverse beams), but the cantilever regions were still failing in shear. At this point, the width of the cantilever regions was increased to 300 mm.

Note: The idea is that when it is certain that a beam is adequate in bending (flexure), the width can be increased in order to reduce the shear stress instead of increasing the depth. However, adequate care must be taken about the detailing and architectural requirements.

At the end of the design and manipulation, the depth and width of the beam that satisfied the ultimate limit state requirements were 900 mm and 400 mm respectively, especially for the cantilever regions. The perimeter beams of the first floor were okay at a depth of 600 mm and width of 230 mm, but in order to avoid any awkward appearance of the building, the depth of the perimeter beams was also taken to 900 mm.

In summary, one of the major issues of transfer structures is shear, and more often than not, you will require more than two legs of reinforcement with very close spacing. It is sometimes recommended that the strut-and-tie method is better for the analysis of transfer beams, especially when it is a deep beam.

Furthermore, architects should bear these challenges in mind when designing buildings that may demand the need for transfer structures by increasing the headroom of the building. When the headroom is high enough, there is enough flexibility for proper design by manipulating the width and depth of the beams as appropriate. The suspended ceiling can drop below beams in order to have a flat ceiling finish that will conceal the irregularities of the beam geometry.

Moreover, it is also important that the design engineer keep formwork (cost, construction, reusability) in mind while manipulating section dimensions. The more uniform the sections, the more economical and easier the building becomes for the owner and the builder.

See the images below for some of the structural details for the beams as produced by Orion (unedited).

transfer%2Bbeam%2Breinforcement%2Bdetails

Note that for bar mark 59 above, you can change the 7H25 to 2 layers

beam%2Bdetails%2B2

Note that there will be a need for sidebars since the depth of the beam is 900 mm. Thank you for visiting Structville today and God bless you.

Do you know that you can partner with Structville to champion infrastructure development in Africa? Send an e-mail to info@structville.com for more information.


Buckling Amplification Factor for Portal Frames Sensitive to 2nd Order Effects

In order to evaluate the sensitivity of a portal frame to 2nd order effects, the buckling amplification factor αcr has to be calculated. This calculation requires the deflections of the frame to be known under a given load combination. Check §5.2.1 of EN 1993-1-1.


In this post, elastic first order analysis is performed on a single bay portal frame using Staad.Pro in order to calculate the reactions under vertical loads at ULS (see figure below). The actions on the portal frames are as given below;

gk = 2.31 kN/m
qk = 3 kN/m

Design load = (1.35 gk) + (1.5 × qk)

Roof load = (1.35 × 2.31) + (1.5 × 3.0) = 3.1185 + 4.5 = 7.6185 kN/m

PORTAL%2BFRAME%2BNHF

When analysed;

Vertical base reaction VEd = 118.263 kN
Horizontal base reaction HEd = 65.651 kN
Maximum Axial Load on rafter NR,Ed = 93.9 kN

Axial Compression in the rafter
According to clause 5.2.1(4), if the axial compression in the rafter is significant, then the αcr is not applicable.

The axial compression is significant if;

λ ̅  ≥ 0.3√((Afy)/NEd ) and this can be rearranged to show that the compression is significant if
NEd ≥ 0.09Ncr

NEd is the design axial load in the rafter
Lcr is the developed length of the rafter pair from column to column;
Lcr = 30/cos 15° = 31.058m
Ncr = (π2EI)/Lcr2 = (π2 × 210000 × 16000 × 104)/310582 = 343789.059 N = 344 kN

0.09Ncr = 0.09 × 344 = 30.94 kN
NEd = 93.9 kN > 30.94 kN, therefore axial load is significant.

When the axial force in the rafter is significant, a conservative measure of frame stability defined as αcr,est may be calculated. For frames with pitched rafters;

αcr,est = min(αcr,s,est ; αcr,r,est)

Where;
αcr,s,est is the estimate of αcr for the sway buckling mode
αcr,r,est is the estimate of αcr for the rafter snap-through buckling mode. This is only relevant when the frame has more than two bays or if the rafter is horizontal.

To calculate αcr, a notional horizontal force (NHF) is applied to the frame, and the horizontal deflection of the top of the column is determined under this load.

HNHF = VEd/200 = 118.263/200 = 0.591 kN


For the assessment of frame stability and for the assessment of deflections at SLS, the base may be modelled with a stiffness assumed to be a proportion of the column stiffness as follows;

  • 10% when assessing frame stability (10% of the column stiffness may be modelled by using a spring stiffness equal to 0.4EIcolumn/Lcolumn)
  • 20% when calculating deflections at SLS (20% of the column stiffness may be modelled by using a spring stiffness equal to 0.8EIcolumn/Lcolumn)

When the software cannot accommodate a rotational spring, the base fixity may be modelled by a dummy member of equivalent stiffness as shown below;

modelling%2Bof%2Bsupport
  • For assessing frame stability, the second moment of area of the dummy member should be taken as Ixx = 0.1Ixx,column
  • For calculating deflection at SLS, the second moment of area of the dummy member should be taken as Ixx = 0.2Ixx,column

In both cases, the length of the dummy member is 0.75Lcolumn and pinned at the far end.

On modelling the nominally pinned base using dummy members, the deflection below was obtained for the notional horizontal forces.

buckling%2Bamplification%2Bfactor%2Bfor%2Bportal%2Bframe

Therefore αcr = h / 200δNHF = 7000/(200 × 2.963) = 11.81
αcr,s,est = 0.8(1 – NEd/Ncr)
αcr = 0.8(1 – 93.9/344)11.81 = 6.869
αcr,s,est = 6.869 < 10

Therefore, second order effects are significant. Since αcr,s,est ≥ 3.0, the amplifier is given by;
[1/(1 – 1⁄αcr,est)] = [1/(1 – 1 ⁄ 6.869)] = 1.17

Note: If αcr,s,est is less than 3.0, second order analysis must be used. The simple amplification is not sufficiently accurate.

Therefore the modified partial factor of safety to account for second order effects are as follows;

γG = 1.17 × 1.35 = 1.5
γQ = 1.17 × 1.5 = 1.75

You can now use these modified partial factors to multiply the characteristic permanent and variable actions. The ultimate vertical action on the rafter (taking into account second order effects)is;

Roof load = (1.5 × 2.31) + (1.75 × 3.0) = 8.715 kN/m

Thank you for visiting Structville today and God bless you.

Uplift Verification of Underground Structures

It is widely recognised that an object will float in water if the weight is less than the upthrust. Upthrust is an upward force exerted by a fluid that opposes the weight of an immersed object. This also applies to structures that are buried under the ground and subjected to groundwater action. Structures such as basements, foundations, underground tanks, and swimming pools are at risk if the dead weight is less than the upthrust, especially when the structure is empty.

According to clause 2.4.7.1 of EC7 (EN 1997-1-1:2004), where relevant, it shall be verified that the following limit states are not exceeded in structures buried under the ground:

  • loss of equilibrium of the structure or the ground, considered as a rigid body, in which the strengths of structural materials and the ground are insignificant in providing resistance (EQU);
  • internal failure or excessive deformation of the structure or structural elements, including e.g. footings, piles or basement walls, in which the strength of structural materials is significant in providing resistance (STR);
  • failure or excessive deformation of the ground, in which the strength of soil or rock is significant in providing resistance (GEO);
  • loss of equilibrium of the structure or the ground due to uplift by water pressure (buoyancy) or other vertical actions (UPL);
  • hydraulic heave, internal erosion and piping in the ground caused by hydraulic gradients (HYO).

Clause 10.2 and 2.4.7.4 of EC7 (EN 1997-1-1:2004) recommends an approach for verifying structures against uplift. Uplift failure (UPL) is verified under the ultimate limit state (ULS) and shall be carried out by checking that the design value of the combination of destabilising permanent and variable vertical actions (Vdst:d) is less than or equal to the sum of the design value of the stabilising permanent vertical actions (Gstb;d) and of any design value of any additional resistance to uplift (Rd).

The limit state check must ensure that;

Vdst:d ≤ Gstb;d + Rd

Where;
Vdst:d = Gdst:d + Qdst:d

The relevant partial factors of safety for the verification are noted in Annex A of BS EN 1997-1 and are shown in the Table below;

ActionStabilizing – FavorableDestabilizing – Unfavourable
Permanent γG0.91.1
Variable γQ01.5

From the above table, it can be seen that variable actions should not be considered when they are favourable to the uplift stability of a buried structure.

In this article, we are going to show how you can verify UPL using Staad Pro software and manual analysis. To check for uplift, we must confirm that the destabilizing actions (both permanent and variable), are less than permanent stabilizing actions. We do not consider favourable variable actions when verifying uplift. Let us look at an example below;

Example
Let us verify the uplift stability of a 3 m x 2 m x 4.0 m concrete tank that is buried under the ground (see figure below). The water table is 1.0 m below the natural ground surface. Thickness of all elements is 350 mm, unit weight of concrete is 25 kN/m3, and unit weight of water is 10 kN/m3. Verify the uplift stability of the tank during construction before the installation of the top slab.

DRAWING%2BFOR%2BTANK

Solution
(a) Stabilizing Forces
Weight of the base = 3.7 x 2.7 x 0.35 x 25 = 87.41 kN
Weight of the walls = 2(3.7 x 4.0 x 0.35 x 25) + 2(2.0 x 4 x 0.35 x 25) = 259 + 140 = 399 kN
Total weight (Gstb) = 486.41 kN

We are neglecting side friction and other possible stabilizing forces

At ultimate limit state, Gstb,d = 0.9 x 486.41 = 437.769 kN

(b) Destabilizing Forces
Head of ground water above the base = 4.35m – 1.0 m = 3.35 m
Vdst,d = (3.7 x 2.7 x 3.35) x 10 = 334.665 kN
At ultimate limit state Vdst,d = 1.1 x 334.665 = 368.131 KN

Vdst,d/Gstb,d = 368.131/437.769 = 0.84 < 1.0 Ok

Therefore the tank is safe against uplift at that stage of construction.

If the structure had failed uplift verification, the remedial actions that could be adopted are;

(1) Increase the thickness of the structural elements and/or projecting the base beyond the walls
(2) Employing drainage and ground water lowering techniques
(3) Introducing anchor piles

To download our publication on design of swimming pools and underground water tanks, click HERE;

front

To download our publication on design of swimming pools and underground water tanks, click HERE;


Propriety of Bending Schedules for Construction Purposes

Structural engineers usually issue bar bending schedule (BBS) to clients/contractors after completing the design and detailing of a reinforced concrete structure. Bar bending schedules usually show the length, shape, and quantity of reinforcements needed for a particular phase/element of a project.

The bar bending schedule issued by structural engineers after a design is usually very exact. In other words, engineers provide the exact quantity of steel needed to produce what they have shown in their drawing, without additional considerations. However, the primary challenge faced by contractors on site is the issue of offcuts, since rebars are usually supplied in 12 m length, and the cut length of reinforcements can vary depending on the element. Offcuts are not usually accounted for in the schedule issued by a structural engineer, and practically, not all offcuts are reusable.

In this case, there are usually two major challenges for the contractor;

(1) He can buy more reinforcement than given in the bending schedule to take care of the losses from offcuts. This usually requires additional calculations.

(2) If the contractor purchases reinforcements based on the bar bending schedule only, he risks requesting for supply twice, which will probably double his transportation cost.

Case Study
To make this point clearer, let us consider this practical scenario below. The ground floor of a 3-storey commercial development is 4.0 m high, and the details of the column reinforcement are as shown below;

STRUCTURAL%2BLAYOUT

CT1 – Column Type 1 (230 x 230)mm – 2 Nos
Main bars: 4Y16
Links: Y10-200 c/c

CT2 – Column Type 2 (450 x 230)mm – 4 Nos
Main bars: 6Y16
Links: Y10-200 c/c

CT3 – Column Type 3 (600 x 230)mm – 2 Nos
Main bars: 8Y20
Links: Y10-250 c/c

CT4 – Column Type 4 (450 x 450)mm – 1 No
Main bars: 12Y20
Links: Y10-300 c/c

At a lap length of 45ϕ (45 x diameter of bar), the typical bending schedule prepared by the structural engineer for the main bars of the ground floor to first floor columns is as follows:

BENDING%2BSCHEDULE

From the above bending schedule, the quantity of steel to be purchased (per 12 m length) for the main bars are as follows;

Y16: [242.28/(1.579 x 12)] = 12.78 (say 13 lengths of Y16mm)
Y20: [343.51/(2.466 x 12)] = 11.61 (say 12 lengths of Y20mm)

As you can see, these quantities are easily verifiable from the bending schedule and could have possibly been used in the preparation of the bill. It is the exact quantity required as given in the drawing.

However, let us go to site and see how this will possibly play out:

The total quantity of bar mark 01 that will need to be cut by the iron bender/fitter is 32 pieces (kindly verify), and the cut length of each bar is 4795 mm. What this means is that he can only obtain 2 pieces of bar mark 01 from each 12m length of reinforcement, and an offcut of 2410 mm. This offcut cannot be used anywhere in the column, except perhaps it gets useful in the beams or other places. Since 32 pieces of bar mark 01 are required, he will need 16 lengths of Y16 mm against the 13 lengths calculated in the bending schedule. Of course, there will be 16 pieces of 2410 mm as offcut!

In the same way, the total quantity of bar mark 02 that will need to be prepared by the iron bender is 28 pieces, and the cut length of each bar is 4975 mm. This also means that he can only obtain 2 pieces of bar mark 02 from each 12m length of reinforcement, with an offcut of 2050 mm. In effect, he will need 14 lengths of Y20 mm against the 12 lengths calculated in the bending schedule.

If the contractor did not make this consideration before requesting for supply, he will likely make his request twice, to the detriment of extra cost. Therefore, the effects of offcuts should be verified by the contractor before he can place his order for reinforcement. This is usually very common, especially for someone who has not experienced it before.

Thank you for visiting Structville today, and God bless you.

Do you need help in knowing the exact quantity of reinforcement that you will need to complete your project without needing to go to the market twice? We are here to help you with that. When you send your drawings to us, we will assess all reinforcements and bar marks independently, and tell you where all offcuts can be reused. We achieve this by issuing a special bending schedule and cutting scheme that takes into account re-usage of offcuts for foundations, beams, slabs, and columns. We will also issue a cutting sequence to the iron bender such that wastage can be minimised as practically as possible. This can save you a reasonable amount of money for your projects, and we do this for a very low fee that is based on the quantity of offcuts that we saved for you. Try us today by sending an e-mail to info@structville.com


Plastic Analysis of Frames

The fully plastic moment of a section (Mp) is the maximum moment of resistance of a fully yielded cross-section. The yielded zone due to bending where infinite rotation can take place at a constant plastic moment (Mp) is called a plastic hinge.

In order to find the fully plastic moment of a yielded section, we normally employ the force equilibrium equation by saying that the total force in tension and compression at that section are equal. In frames, the plastic moment can be easily obtained using the kinematic method (upper bound theorem).

When a system of loads is applied to an elastic body, it will deform and show some resistance to deformation, and such a body is called a structure. On the other hand, if no resistance is set up against deformation, such as a body is said to have formed a mechanism. This can occur in structures such as beams and frames.

One of the fundamental conditions for plastic analysis of a framed structure is that the collapse load is reached when a mechanism is formed, in which the number of plastic hinges developed in the structure is sufficient to form a mechanism. The load factor (λ) at rigid plastic collapse is the lowest multiple of the design load which will cause the whole structure or part of it to form a mechanism.

It is important to realise that the number of independent mechanisms in a structure is related to the number of plastic hinge locations and the degree of redundancy of the system.

In beams, identification of critical spans in terms of Mp or load factor can be obtained using the static or kinematic method by considering simple beam mechanisms. But in framed structures, other types of mechanisms such as joint, sway, and gable mechanisms are also considered. Each of these mechanisms can occur independently, but it also possible for a critical collapse mechanism to develop by combination of the independent mechanisms.

Beam and sway mechanism in a framed structure
Beam and sway mechanism in a framed structure

The purpose of combining mechanisms is to eliminate hinges that exist in the independent mechanism leaving only the minimum number required in the resulting combination to induce collapse.

The steps in the plastic analysis of frame structures are as follows;

  1. Calculate the degree of static indeterminacy of the structure (RD)
  2. Calculate the number of possible plastic hinges (RD + 1)
  3. Identify the independent collapse mechanisms and evaluate them
  4. Combine the independent mechanism and eliminate hinges where applicable
  5. Obtain the critical plastic moment Mp which is the highest bending moment in the structure
  6. Check for equilibrium and evaluate the reactive forces
  7. Plot the final plastic moment diagram. No bending moment at any point in the structure should exceed the critical plastic moment.

Solved Example
For the frame loaded as shown below, find the critical Mp value, and draw the collapse moment diagram. The loads are factored.

PLASTIC%2BANALYSIS%2BOF%2BFRAMES

Degree of static indeterminacy
RD = (3m + r) – 3n
m (number of members) = 4
r (number of support reactions) = 5
n (number of nodes) = 5
R= (3 × 4 + 5) – 3(5) = 2
Therefore the frame is indeterminate to the second order.

A little consideration will show that the possible places where we could have plastic hinges in the structure are at node B, section C, section D (just to the left), section D (just to the right), section D (below) and section F. Nodes A, E, and F are all natural hinges. Therefore, total number of possible hinges = 6

Hence, number of independent collapse mechanisms = 6 – 2 = 4

These independent mechanisms are listed below;
– 2 Beam mechanisms (span B – D and span D – G)
– 1 sway mechanism of the entire frame due to the horizontal load
– 1 joint mechanism

Analysis of the independent mechanisms

Mechanism 1

Mechanism%2B1

δC = 3 × θ = 3θ
Internal work done due to rotations at internal hinges at B, D, and C
Total internal work done (Wi) = Mpθ + Mpθ + 2Mpθ = 4Mpθ

External work done (We) = 115 × 3θ = 345θ

Let external work done = Internal work done
4Mpθ = 345θ
On solving, Mp = 345/4 = 86.25 kNm

Mechanism 2

Mechanism%2B2

δF = 3 × θ = 3θ
Internal work done due to rotations at internal hinges at B, and F. No work is done at G because it is a natural hinge.
Total internal work done (Wi) = Mpθ + 2Mpθ = 3Mpθ

External work done (We) = 74 × 3θ = 222θ

Let external work done = Internal work done
3Mpθ = 222θ
On solving, Mp = 222/3 = 74 kNm

Mechanism 3 (Sway)

sway%2Bmechanism

δ1 = 4 × θ = 4θ
Internal work done due to rotations at internal hinges at B, and D. No work is done at A, E, and G because they are all natural hinges.

Total internal work done (Wi) = Mpθ + Mpθ = 2Mpθ

External work done (We) = 25 × 4θ = 100θ

Let external work done = Internal work done
2Mpθ = 100θ
On solving, Mp = 100/2 = 50 kNm

Mechanism 4 (Joint Rotation)

Joint%2BMechanism
clockwise%2Brotation

Internal work done = Mpθ + Mpθ + Mpθ = 3Mpθ
External work done = 0 (no external work done)

Anticlockwise%2Brotation

Internal work done = Mpθ + Mpθ + Mpθ = 3Mpθ
External work done = 0 (no external work done)

Let us now consider the possible mechanism combination by preparing the table below

table%2Bcombined%2Bmechanism

The critical Mp is therefore = 111.167 kNm (This was achieved after other combinations were considered but this was found to be the highest).


Note that by virtue of the combination, internal hinges at B, D2, and D3 were eliminated. So the critical collapse mechanism is as given below;

collapse%2Bdiagram
SUPPORT%2BREACT

Note that the implication of our analysis above is that points C, F and D1 are plastic hinges, with a full plastic moment of 111.167 kNm. While C and F are sagging, D1 is hogging. No other bending moment in the structure should exceed this value. Once a higher moment is discovered, it means that the critical collapse moment was not appropriately obtained.

∑MFR = 0 (anti clockwise positive)
3VG = 111.167
VG = 37.056 kN

∑MCL = 0 (clockwise positive)
3VA – 4H= 111.167 ———– (1)

∑MDL = 0 (clockwise positive)
6VA – 4H– (115 × 3) = -111.67
6VA – 4H= 233.833 ———– (2)

Solving (1) and (2) simultaneously;
VA = 40.721 kN
HA = 2.623 kN

∑MA = 0 (clockwise positive)
12VG + 6V– (74 × 9) – (115 × 3) – (25 × 4) = 0
6V= 666.328
VE = 111.055 kN

∑Fx = 0
H= 25 + 2.623 = 27.623 kN

reactive%2Bforces

Bending Moment
You can verify that having obtained the support reactions, the bending moment diagram can easily be plotted without strenuous calculations.

bmd


Thank you for visiting Structville today, and God bless you.

How to Analyse Retaining Walls for Trapezoidal Load

In the analysis of retaining walls subjected to earth pressure, it is very common to observe trapezoidal load distribution on the walls. Normally, earth pressure on a retaining wall is assumed to adopt a triangular load distribution, but due to surcharge which is usually assumed to act on the ground surface, the top of the wall experiences some degree of lateral pressure.


When the top of a retaining wall is free and the base assumed to be fixed, the retaining wall can be analysed easily using the three equations of equilibrium by modelling the wall as a cantilever. The load cases of surcharge, earth pressure, and ground water can be analysed separately, and the results added algebraically. When the wall top of a wall is propped, a statically indeterminate behaviour is assumed, and the wall can be analysed using the theory of plates and shells.

Numerous approaches such as finite difference method, finite element analysis, classical theory, etc can be adopted to solve problems of such nature. Anchor (1992) adopted a convenient approach of replacing the surcharge pressure with equivalent soil pressure. This was done by adding the maximum soil pressure and surcharge pressure algebraically, and assuming an equivalent triangular distribution. Another approach recommended by Reynolds et al (2008) is to separate the load cases, analyse them separately, and sum the results together. For walls spanning in two directions, this method is accurate for edge bending moments, but approximate for span moments.

SECTION%2BTANK

In this post, we are going to explore the behaviour of the walls of a tank subjected to earth pressure and surcharge pressure (find the section of the tank above). We are going to investigate the methods described above, and compare them with finite element analysis using Staad Pro software.

Let us consider a propped cantilever wall loaded as shown below. The pressure at the top of the wall represents the surcharge pressure at ULS, while the pressure at the bottom of the wall represents the combined pressure of surcharge and retained earth at ULS.

TRAPEZOIDAL%2BLOAD%2BON%2BRETAINING%2BWALL

(1) By plate theory

We are going to analyse the walls using coefficients that can be readily obtained from charts and tables. We will separate the trapezoidal load into its triangular and rectangular components as shown below, and analyse them separately;

COMONENTS

Using Moment Coefficient from Table
Note that these coefficients contain allowance for torsion at the edge, and are picked from Reynolds et al (2008).

Vertical Span
Maximum negative moment at base (triangular) = 0.048 × 70.599 × 4.32 = 62.658 kNm/m
Maximum negative moment at base (rectangular) = 0.073 × 5.625 × 4.3= 7.592 kNm/m
Total Moment negative base moment = 62.658 + 7.592 = 70.250 kNm

Maximum positive moment (triangular) = 0.0185 × 70.599 × 4.32 = 24.149 kNm/m
Maximum positive moment (rectangular) = 0.055 × 5.625 × 4.32 = 5.720 kNm/m
Total approximate mid-span moment = 24.149 + 5.720 = 29.869 kNm/m

Horizontal Span
Maximum negative moment at the edge (triangular) = 0.033 × 70.599 × 4.32 = 43.077 kNm/m
Maximum negative moment at the edge (rectangular) = 0.032 × 5.625 × 6.42 = 7.3728 kNm/m
Total Moment negative edge moment = 43.077 + 7.3728 = 50.449 kNm

Maximum positive moment (triangular) = 0.011 × 70.599 × 4.32 = 14.359 kNm/m
Maximum positive moment (rectangular) = 0.024 × 5.625 × 6.42 = 5.5296 kNm/m
Total positive moment = 19.886 kNm/m


(2) By Equivalent Pressure Method

method%2B2

We are going to analyse the pressure load on the wall by summing up the pressure due to retained earth and surcharge and analysing them as triangular distribution.

Vertical Span
Maximum negative moment at the base base  = 0.048 × 76.224 × 4.32 = 67.65 kNm/m
Maximum positive moment at the span = 0.0185 × 76.224 × 4.32 = 26.073 kNm/m

Horizontal Span
Maximum negative moment at the edge = 0.033 × 76.224 × 4.32 = 46.509 kNm/m
Maximum positive moment (triangular) = 0.011 × 76.224 × 4.32 = 15.503 kNm/m

(3) By Finite Element Analysis Using Staad Pro

When modelled and analysed on Staad Pro;

FEA%2B1
FEA%2B3
FEA2
FEA4

We will have to allow for torsion at the edge moments.


By using Staad Pro;

Vertical Span
Maximum negative moment at base = 58.9 kNm/m (allowing for torsion = 71.7 kNm/m)
Maximum positive moment (mid span) = 31.2 kNm/m

Horizontal Span
Maximum negative moment at edge = 40 kNm/m (allowing for torsion = 52.8 kNm/m)
Maximum positive moment = 18 kNm/m

Twisting moment = 12.8 kNm/m

Let us compare the results from the three methods investigated;

Table

From the above table, it can be seen that the result from the use of coefficient and FEA are very close and comparable, while the result using equivalent approach is giving lower bound results. Therefore, in the absence of computer programs, I recommend the use of coefficients from Table for analysis of retaining walls subjected to trapezoidal loads.

This post is an excerpt from the book;

Structural Design of Swimming Pools and Underground Water Tanks‘ by Ubani Obinna. Published by Structville Integrated Services Limited (2018). ISBN 978-978-969-541-6

front

To obtain this publication in PDF for NGN 2,000, click HERE
For more information, send a Whatsapp message to;
+2347053638996

References
Anchor R.D. (1992): Design of Liquid Containing Structures. Published by Edward Arnolds, UK. ISBN 0-340-54527-5

Reynolds C.E., Steedman J.C., Threlfall A.J. (2008): Reynolds Reinforced Concrete Design Handbook. Spon Press, Taylor and Francis Group (11th Edition)

Ubani O.U. (2018): Structural Design of Swimming Pools and Underground Water Tanks. Structville Integrated Services Limited (2018). ISBN 978-978-969-541-6